TPC Collaboration Meeting, Copenhagen, 2-3 September 2002
Niels Bohr Institute
|
List of action items from Copenhagen meeting 2-3.9.02 (P. Glässel)
Resistive rod decision:
monthly status monitoring
clarify compatibility of material in contact with high resistivity
water
full scale prototypes must be available for water-cooled rods and for
gas-cooled rods with retractable contacts before the end of 02 to
prepare a decision
glue for the rods needs to be defined
IROC production in Bratislava:
built first chamber now with existing setup and improved glueing but
unchanged combs; check performance of this chamber
check whether grooves for thicker wires are same in Bratislava
Herbert: check Bratislava production notes whether you agree with
procedures
Ageing tests:
urgent for 190 Araldite
tests to be done with recirculating gas system
GSI (H. Sann) to finish recirculating gas sysem by end Sept
Muon Al absorber plate:
interference with chamber mounting tool: can tool be shortened (Bernd)?
consequence otherwise that chambers on MUON side not serviceable in
working position of TPC
Gas system:
distribution manifold on TPC NOT part of GWG job
TTC test setup
urgently needed to test RCU functionality
FEE mail list:
who is on, who is missing? (Luciano)
PASA and FEC test software urgent item:
pbm will coordinate actions with R. Renfordt and H. Oeschler.
Solution to be found within 4 (!) weeks
PASA test hardware:
time plan too late, should be available for testing of engineering
run, i.e. Jan 03; outside help needed?
DCS:
specify and procure temperature sensors for TPC vessel (Uli?)
HV:
power failure precautions necessary?
ramping procedure to be defined / tested (Wolfgang)
Inner thermal screen:
decision no later than spring 03 with input from and in collaboration
with the ITS community